Weifang site visit-1 April 2002
Weifang site visit-2 April 2002
Establishment of Working Group in Fukuoka
Installatioon of underground water collection pipes September 2003
Leachate collection pipes Joint part of main and branch pipes
Installation of leachate collection pipes and gas ventilationo pipes September 2003
Installation of gas ventilation pipes
Installation of liner sheet on the side slope
Liner sheet connected September 2003
1st stage construction completed October 2003
Leachate control pond
Leachate treatment facility in the landfill
Waste disposal has been started in the new landfill since October 2003
Fukuoka Method Landfill Workshop in Weifang City November 2003
Environment monitoring staff and equipment
Measurement of gas concentration rate June 2004